Yucca Trail Safety Improvements, Project #8971

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Description:

The Town has been awarded grant funds through the HSIP. The project involves the the installation of traffic safety improvements on Yucca Trail. Yucca Trail, from Warren Vista Avenue to Avalon/Palomar Avenue. Widening Yucca Trail by providing an 8 foot shoulder on both sides. 2-12’ travel lanes. 12 foot center striped median with left turn movements into the intersections of Warren Vista, Bonita, Chula Vista, Victoria, Alaba, Frontera, Balsa, Emerson, Hanford, La Habra, Rubidoux, and Palomar. Widening of Warren Vista both north and south of Yucca Trail to include left hand turn and through lanes. In addition to the improvements to the similar intersection improvements at Yucca Trail and Palomar.

Design Firm:

Albert Webb Associates

Contractor:

Matich Corporation

Schedule:

Construction Started

November 30, 2020

Construction Completed

March 3, 2021

 

Funding:

Fund 526 - HSIP Grant Funds (Programmed Federal Funds)

$969,660.00

Fund 350 – DIF-Development Impact Fees (Matching Local Funds)

$467,534.00

Total Construction Funding

$1,437,194.00

 

Estimated Project Cost:

Environmental and Design Phase

$167,272.93

External Consulting (NAI)

$14,202.50

Miscellaneous (Publishing)

$2,786.09

Construction Cost

$1,233,270.54

Total Project Cost

$1,417,532.06

 

Additional Information:

Yucca Trail Improvement Project - Photos

Yucca Trail Improvement Project -Plans