Yucca Valley, CA
Home MenuTown-Wide Slurry Seal Project, Town Project No.8340-2022
Project Description:
The Town Wide Slurry Seal Project is an annual maintenance effort that is a part of the Town’s overall pavement maintenance program. The annual maintenance effort is implemented to extend the lifetime of the roadway pavement throughout the Town prior to roads deteriorating to the degree where road reconstruction is necessary. The annual slurry seal project generally consists of applying a Type II Slurry Seal to the roadway, crack sealing of all candidate streets, as well as replacement of obliterated traffic striping and damaged raised pavement markers (RPM’s).
Design Firm:
Town of Yucca Valley
Contractor:
VSS International
Tentative Schedule:
Construction Begins |
June 2022 |
Construction Ends |
July 2022 |
Funding:
Fund 801 Measure Y | $ 1,100,000.00 |
Estimated Project Cost:
Estimated Construction Cost | $ 880,120.00 |
The anticipated project expenditures for 2021/2022 Town-wide slurry program are $ 1,091,320.00 and includes the construction cost plus 10% contingency, admin/inspection, and indirect cost recovery.
Construction Cost |
$ 880,120.00 |
10% Contingency |
$ 88,000.00 |
Administration /inspection (3%) |
$ 26,400.00 |
Indirect Recovery Cost (11%) |
$ 96,800.00 |
Total Project Cost |
$ 1,091,320.00 |