Home MenuPalomar Avenue/Yucca Trail Intersection Improvements Project #8969
Project Description:
The project consists of the widening of Palomar Avenue north and south of Yucca Trail, to provide left turn lanes, through lanes, right turn lanes, and traffic signal modification at the intersection between Yucca Trail and Palomar Avenue.
Design Firm:
Albert Webb Associates
Procurement of Traffic Signal Poles:
McCain Inc
Contractor:
American Asphalt
Schedule:
Construction Started |
November 30, 2020 |
Construction Completed |
May 28, 2021 |
Funding:
The Yucca Trail/Palomar Avenue Intersection Improvements Project (Town Project No. 8969-2020) was included in the FY2020/21 Budget, and it was programed for design and construction in Fund 350 Development Impact Fees (DIF) in the amount of $504,743.00 as shown below.
Fund 350 – Development Impact Fees (DIF)
Yucca Trail / Palomar Improv (Environ & Design) |
$ 80,643.00 |
Yucca Trail / Palomar Improv (Construction) |
$ 424,100.00 |
Total Fund 350 DIF = |
$ 504,743.00 |