Home MenuOnaga Trail Pedestrian Improvement Project, Town Project No. 7005-2020; ATP No. 5466(025)
Project Description:
The Town has been awarded grant funds through the Active Transportation Program (ATP). The project is located on Onaga Trail between Acoma Trail and approximately Grand Avenue. It is divided in two segments from Acoma Trail to Church Street and from Church Street to Grand Avenue. Both segments would have full width pavement, curb and gutter, handicap ramps, and sidewalk on both sides of Onaga Trail. This would result in sidewalks on both sides of Onaga Trail, between Sage Avenue and Acoma Trail.
Design Firm:
KOA Corporation
Contractor:
TBD
Tentative Schedule:
Design Completed |
March 2022 |
CalTrans Authorization for Construction |
April 2022 |
Construction Bidding |
October 2023 |
Construction Begins |
January 2023 |
Construction Ends |
April 2023 |
Funding:
This project is funded through the Active Transportation Program (ATP) grant funds and matching local funds.
Engineering Design |
|
|
|
FUND 524 - Measure I |
$ 85,000.00 |
|
FUND 536 – ATP Grant |
$ 52,000.00 |
|
FUND 800 – Capital Projects Reserve |
$ 19,000.00 |
Total Engineering Design Budget |
$156,000.00 |
|
Construction |
|
|
|
FUND 536 - ATP Grant |
$724,000.00 |
|
FUND 517 – RMRA |
$556,000.00 |
|
FUND 524 - Measure I |
$1,068,674.00 |
Total Construction Budget |
$ 2,348,674.00 |
|
Total project Budget |
$ 2,504,674.00 |
Estimated Project Cost:
PA/ED (ENVIRONMENTAL) |
|
$ - |
PS&E |
|
$ 155,995.00 |
ROW/Property Acquisition |
|
$ - |
CONSTRUCTION |
|
$ 1,792,760.00 |
CONTINGENCY (15%) |
|
$ 268,914.00 |
CONSTRUCTION TOTAL |
|
$ 2,061,674.00 |
CONST. ADMIN. |
|
|
Inspection |
|
$ 11,900.00 |
Material Testing |
|
$ 23,800.00 |
Surveying |
|
$ 36,000.00 |
INDIRECT COST |
|
$ 131,000.00 |
TOTAL PROJECT COST (ESTIMATE) |
$ 2,420,369.00 |
Additional Information:
YV Onaga Trail Improvements-2022