Onaga Trail Pedestrian Improvement Project, Town Project No. 7005-2020; ATP No. 5466(025)

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Description:

The Town has been awarded grant funds through the Active Transportation Program (ATP). The project is located on Onaga Trail between Acoma Trail and approximately Grand Avenue. It is divided in two segments from Acoma Trail to Church Street and from Church Street to Grand Avenue. Both segments would have full width pavement, curb and gutter, handicap ramps, and sidewalk on both sides of Onaga Trail.  This would result in sidewalks on both sides of Onaga Trail, between Sage Avenue and Acoma Trail.

Onaga Trail Photo

Design Firm:

 KOA Corporation

Contractor:

 TBD

Tentative Schedule:

Design Completed

March 2022

CalTrans Authorization for Construction

April 2022

Construction Bidding

October 2023

Construction Begins

January 2023

Construction Ends

April 2023

 

Funding:

This project is funded through the Active Transportation Program (ATP) grant funds and matching local funds.

Engineering Design

 

 

FUND 524 - Measure I

$ 85,000.00

 

FUND 536 – ATP Grant

$ 52,000.00

 

FUND 800 – Capital Projects Reserve

$ 19,000.00

Total Engineering Design Budget

$156,000.00

Construction

 

 

FUND 536 - ATP Grant

$724,000.00

 

FUND 517 – RMRA

$556,000.00

 

FUND 524 - Measure I

$1,068,674.00

Total Construction Budget

$ 2,348,674.00

Total project Budget

$ 2,504,674.00

Estimated Project Cost:

PA/ED (ENVIRONMENTAL)

 

$ -

PS&E

 

$ 155,995.00

ROW/Property Acquisition

 

$ -

CONSTRUCTION

 

$ 1,792,760.00

CONTINGENCY (15%)

 

$ 268,914.00

CONSTRUCTION TOTAL

 

$ 2,061,674.00

CONST. ADMIN.

 

 

Inspection

 

$ 11,900.00

Material Testing

 

$ 23,800.00

Surveying

 

$ 36,000.00

INDIRECT COST

 

$ 131,000.00

TOTAL PROJECT COST (ESTIMATE)

$ 2,420,369.00

Additional Information:

YV Onaga Trail Improvements-2022

Public Outreach Meeting - Onaga Trail Improvements