North Park Improvements Project, Town Project No. 8950-2021; CDBG Project No. TYVA-20-1-03F/0173.

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Description:

The North Park Improvements Project consists of the installation of an ADA accessible single-family restroom; a paved parking lot with ten (10) parking spaces and two additional accessible parking spaces, unpaved parking area with capacity for 28 parking spaces, a 20-foot-wide paved drive access to the parking lot from Fairway Drive, utility connections and a trail of approximately 600 feet to connect the parking lot with the existing area used by locals and visitors for parking.

Design Firm:

ERSC Inc 

Contractor:

The Van Dyke Corporation

Tentative Schedule:

RFP for Construction

December 21, 2021

Construction Bid Opening

February 2, 2022

Award Construction Contract

February 2022

Construction Begins

March 2022

Construction Ends

May 2022

 

Funding:

FUND 560 - CDBG North Park

$ 449,681.00

FUND 801 – Measure Y

$ 195,000.00

Total Budget

$ 644,681.00

Estimated Project Cost:

Publishing / Advertising

$1,183.00

Miscellaneous

$ 100.00

NRO Engineering (Town Engineer)

$ 3,875.00

Design (ERSC Inc) - CDBG authorized 4/27/21

$ 59,575.00

Design Changes (ERSC Inc) Contract Amendment No 1

$ 8,065.00

Native Plants Mitigation Fees and Outsource Services

$ 33,315.00

Construction Costs

$ 445,377.00

Administration and Inspection

$ 31,451.00

Construction Surveying (ERSC Inc.) Contract Amendment No 1

$ 12,630.00

Indirect Recovery Cost

$ 43,246.00

TOTAL ESTIMATED COSTS

$ 638,817.00

Additional Information:

North Park Plans