Project Description:
The project is located on Little League Drive between Sage Avenue to Palm Avenue. The Project consists of constructing curb and gutter, sidewalk, handicap ramps, driveways, and signing and striping. The majority of the work will occur on the south side of the roadway. Portions of the road already have curb and gutter so no widening will occur in those locations; however, curb ramps at the intersections may need to be installed/retrofitted. The overall project length is approximately 2,600 feet.
Design Firm:
KOA Corporation
Contractor:
TBD
Tentative Schedule:
Design Completed |
March 2022 |
CalTrans Authorization for Construction |
April 2022 |
Construction Bidding |
October 2022 |
Construction Begins |
January 2023 |
Construction Ends |
April 2023 |
Funding:
Engineering Design |
|
|
|
FUND 536 – ATP Grant |
$ 68,000.00 |
|
FUND 800 – Capital Project Reserve |
$ 19,000.00 |
Total Engineering Design Budget |
$ 87,000.00 |
|
Construction |
|
|
|
FUND 536 – ATP Grant |
$ 554,000.00 |
|
FUND 517 – RMRA |
$ 150,000.00 |
|
FUND 524 – Measure I |
$ 210,000.00 |
Total Construction Budget |
$ 914,000.00 |
|
Total project Budget |
$ 1,001,000.00 |
Estimated Project Cost:
The total estimated project cost is:
PA/ED (ENVIRONMENTAL) |
|
$ - |
PS&E |
|
$ 79,910.00 |
ROW/Property Acquisition |
|
$ - |
CONSTRUCTION |
|
$ 719,200.00 |
CONTINGENCY (10%) |
|
$ 71,920.00 |
CONSTRUCTION TOTAL |
|
$ 791,120.00 |
CONST. ADMIN. |
|
|
Inspection |
|
$ 6,700.00 |
Material Testing |
|
$ 13,200.00 |
Surveying |
|
$ 19,700.00 |
INDIRECT COST |
|
$ 79,100.00 |
TOTAL PROJECT COST (ESTIMATE) |
$909,820.00 |
It may be necessary to appropriate additional funds at the time of construction bid award, based upon budgeted funds and estimated construction costs.